General Director visits and encourages Ninh Binh Nitrogenous Fertilizer and Chemical Limited Company Staff during Major Overhaul in 2026

05:11 PM @ Monday - 09 November, 2026

On 9 November 2026, Mr. Nguyễn Hữu Tú, General Director of Vietnam National Chemical Group, visited, inspected the progress of the major maintenance works, and encouraged staff and workers of Ninh Binh Nitrogenous Fertilizer and Chemical Limited Company during its 2026 overhaul.

The delegation included Mr. Lê Hoàng, Deputy General Director of the Group; Mr. Nguyễn Huy Thông, Chairman of the Vietnam Chemical Industry Trade Union; and representatives of specialist departments.

The major overhaul of Ninh Binh Nitrogenous Fertilizer and Chemical Limited Company commenced on 11 October 2026, with a total scheduled plant shutdown, maintenance, and restart period of 40 days. This is a significant overhaul, focusing on numerous crucial technological equipment items, requiring high technical standards and close cooperation among participating units.

Reporting to the delegation, company leadership confirmed that as of 9 November, the maintenance process was progressing actively, with main items essentially on schedule. Several key tasks had been completed, including the major overhaul of equipment in the Heat Workshop and replacement of components in the gasification furnace. Some maintenance works in the Ammonia, Urea workshops and auxiliary systems were being urgently finalised.

For items with complex technical requirements, the company identified additional unforeseen damage during dismantling and inspection. In response, it proactively coordinated with specialist units, contractors, and experts to assess equipment conditions and select appropriate repair, restoration or replacement solutions. Additional works were managed concurrently with main tasks to minimise impact on overall progress.

Notably, some major items in the air separation area were being prioritised for manpower, equipment, and specialist attention to complete installation, alignment, and technical checks. Waterproofing for the granulation tower in the Urea workshop was also being expedited. With a proactive and determined spirit, the company’s staff, engineers, and workers were making every effort to overcome difficulties and complete all tasks as planned.

In addition to progress and repair quality, occupational safety, industrial hygiene, and environmental protection were always prioritised by the company. Work permits, equipment checks, the provision of personal protective equipment and on-site supervision were strictly implemented, especially for high-risk tasks such as working at height, in confined spaces, and on complex technological equipment.

During his visit and inspection, Mr. Nguyễn Hữu Tú, General Director of the Group, enquired after and encouraged the engineers, technicians, workers, and staff directly involved in the overhaul. The care of the Group’s leadership and Trade Union demonstrated their support and solidarity with the workforce during the period when the plant was shut down to undertake this major workload.

According to plan, the company is focusing on completing critical items, organising checks, trial runs, and gradually bringing equipment systems back into operation. On 11 November, the thermal power boiler is scheduled to be ignited; on 16 November, the gasification furnace will be fired, and by 18 November 2026, Urea production will resume.

The 2026 major overhaul is of great significance in maintaining and enhancing equipment reliability, ensuring safe, stable, and efficient production operations. The close attention and guidance of the Group’s leadership, along with the responsibility and effort of Ninh Binh Nitrogenous Fertilizer and Chemical Limited Company’s staff and workers, are key drivers for successfully completing the maintenance works, quickly bringing the plant back to operation, and contributing to the achievement of the 2026 business and production plan.